Sample takeoff · Ungated · Public record
This is what your free takeoff looks like.
A finished quantity survey from a closed public bid — 37 lines, 27 proven by two independent sources, 3 by one, and the 7 the documents could not support named with the sheet each failed on, instead of guessed. Send one invitation you are bidding now and the complete takeoff comes back inside 2 business days, free.
Reply < 1 hr · Takeoff < 2 business days · No card · No login · No software
Nursultan Temirbaev, estimator of record — Indian Trail, NC · (980) 348-1827
Community College Cosmetology Center Renovation — single-storey interior renovation, four trades. NC eVP solicitation 132-WPCC-2026 — bid opened 14 July 2026, closed. Documents are public record. Mindatu did not bid this project and holds no interest in it. There is no pricing in this deliverable, by design: at the survey tier we measure and prove, and you apply your own rates.
How to read the tiers
Three grades. One rule.
27 GOLD · 3 SILVER · 7 FLAGGED · 10 open items named. Every line carries the basis it rests on, so you judge it yourself rather than take our word.
The quantity is fixed by two sources that were produced independently of each other — a schedule and a specification section, or two measurements by different mechanisms. Price it with confidence.
One defensible read. Sound for pricing, and the basis is printed beneath every line, so you can judge it yourself rather than take our word.
The documents cannot support a number, or they contradict themselves. We name the gap and what would close it. We never close a gap with an assumption and then report it as a quantity.
Worked example · why one line is SILVER, not GOLD
Acoustical ceiling — the second measure that did not agree
The ceiling area was measured room by room and then attacked a second way, by reconstructing the drawn 2×2 grid lattice off the reflected ceiling plan and integrating it. Three separate mechanisms were tried. The horizontal and vertical passes of the lattice disagreed by 51%, 26% and 56% across those attempts — because the grid is drawn at full density in some rooms, omitted in others, and overlaid by an existing ceiling that is scheduled to remain. Two independent mechanisms that disagree past 10% do not produce a number. So the ceiling quantity carries one defensible read and is marked SILVER, not GOLD, and this paragraph is the reason. We publish the attempt that failed because an estimator pricing this scope needs to know which of our numbers is carried by one method and which by two.
The schedule · 37 lines · numbered as published
Every line, the basis it rests on, and its grade.
Five packages. The line numbers are the ones the forward email refers to — line 9 is the first FLAGGED.
Acoustical Ceilings
26 ceiling areas across 20 scheduled rooms; two panel systems, both 24×24, plus custom edge trim and an existing ceiling to remain.
| # | Quantity & the basis it rests on | Value | Grade |
|---|---|---|---|
| 01 | Acoustical panel ceiling, total scheduled area, 26 roomsMachine measurement calibrated to the printed life-safety room table; seven independent printed room areas validated the calibration within ±6%. Second mechanism (grid-lattice integration) did not converge — see worked example. | 10,340 SF | SILVER |
| 02 | AC-1 — Armstrong Ultima 1910, 24×24×3/4", square edge, LR 0.88, CAC 35, NRC 0.75Finish schedule room-by-room; product from Section 095113 §2.2 | 14 rooms | GOLD |
| 03 | AC-2 — Armstrong Georgian High Washability 794, 24×24×5/8", square edge (Women's RR, Family RR)Finish schedule; Section 095113 §2.3. Note: the drawing legend calls AC-2 'moisture resistant'; the spec product is a high-washability face. Same item, different words — flagged for the RFI list. | 2 rooms | GOLD |
| 04 | Grid — direct-hung, wide-face capped double-web steel, 15/16" face, intermediate duty, whiteSection 095113 §2.4, serves both panel types | 1 LS | GOLD |
| 05 | Hold-down clips required — Corridors 103 and 160Section 095113 §2.5.B names the rooms | 2 rooms | GOLD |
| 06 | AC-MT — Armstrong Axiom Classic perimeter trim, 2" high, white, at Electrical Room 114, transitioning to existing gridSection 095113 §2.6 + finish schedule | 1 room | GOLD |
| 07 | Attic stock — 10 full-size panels of each typeSection 095113 §1.4 | 20 panels | GOLD |
| 08 | Janitor/Mechanical 187 — open to structure, no ceilingFinish schedule, ceiling column reads O.T.S. | 1 room | GOLD |
| 09 | Ceiling heights vary 10'-0" to 11'-6" by room; the drawn tags are legible but no single height governsHeights read per room off the RCP; any pricing that assumes one height across the job will be wrong | not resolved | FLAGGED |
Drywall & Metal Framing
Six partition families, two of them existing. Board and finish level are specified; the extent of each family is carried only by the drawings.
| # | Quantity & the basis it rests on | Value | Grade |
|---|---|---|---|
| 10 | Partition families: S2.1S (6" stud to deck, board one side), S8S (8" stud to deck), S8.1S (8" stud to deck, board one side), S1E (existing, to 8" above ceiling), plus bracing and deflection detailsPartition-type schedule, sheet A0200 | 6 types | GOLD |
| 11 | Gypsum board — ASTM C1396, Type X, 5/8", tapered edge, on studs at 16" o.c. maxSection 092900 §2.2 + partition details | 5/8" Type X | GOLD |
| 12 | Finish level — Level 4 at all exposed-to-view surfaces; Level 1 at concealed plenumSection 092900 §3.2.C | Level 4 | GOLD |
| 13 | Non-structural metal framing, AISI S220, min base steel 0.0179", depth per drawings, slip-type head jointSection 092216 | 25 ga min | GOLD |
| 14 | Sound attenuation blanket, full height of partition 'if applicable'; 2" blanket laid across the top of S1E partitions extending 4'-0" each sidePartition details name the product and the condition; the spec section gives no locations, so extent is drawings-only | 3" full height | SILVER |
| 15 | New partition run, order-of-magnitude onlyDerived from room-polygon perimeter with a shared-wall correction. The polygons over-segment and the correction is an assumption, not a measurement. This number is published as a range indicator and must not be priced from. Resolve by scaling the partition runs directly off A0200. | ~850 LF | FLAGGED |
| 16 | Moisture- or mold-resistant board typeSection 092900 §2.2 lists only standard and Type X. Two restrooms and a janitor room receive epoxy paint; no wet-area board is specified. RFI. | not specified | FLAGGED |
| 17 | Level 5 finishNot specified anywhere, though P-1 and P-3 are water-based catalyzed epoxy topcoats over gypsum — a system commonly paired with Level 5. Confirm Level 4 is intended. | not specified | FLAGGED |
Flooring & Base
Three floor systems and one base, all specified. Sealed concrete dominates; luxury vinyl tile in the wet and office rooms.
| # | Quantity & the basis it rests on | Value | Grade |
|---|---|---|---|
| 18 | SC-1 — sealed concrete: Armorseal Rexthane pigmented aliphatic urethane, 2 coats, SW 7642 PavestoneFinish schedule room-by-room; Section 099123 §2.6 + §3.5.A | 14 rooms | GOLD |
| 19 | LVT-1 — Mannington Color Anchor Prisma, London Fog C239, 12×24, 2.5 mm, brick pattern, full-spread adhesiveFinish schedule; Section 096519 §2.2 | 3 rooms | GOLD |
| 20 | LVT-2 — same product line, Jade C273, Corridor 160 (with SC-1)Finish schedule; Section 096519 §2.2 | 1 room | GOLD |
| 21 | RB-1 — thermoset rubber cove base, Style B, 4" high × 1/8", job-formed cornersFinish schedule; Section 096513 §2.1 | all rooms | GOLD |
| 22 | Roppe #22 reducer strip at 1/8" LVT transitionsSection 096513 §2.2 | at LVT edges | GOLD |
| 23 | Attic stock — 10% of LVT from the same dye lot; 20 LF of base per colourSections 096519 §1.5, 096513 §1.3 | 10% / 20 LF | GOLD |
| 24 | Base linear footage by roomBase follows room perimeter, and the room-perimeter measurement is the same over-segmented figure flagged under partitions. Same resolution: scale off the plan. | not resolved | FLAGGED |
| 25 | Floor preparation / existing slab conditionA urethane sealer over an existing slab in a renovation is condition-dependent; the documents carry no floor-prep scope. This is the single largest unpriced risk in the flooring package. | not specified | FLAGGED |
Doors, Frames & Openings
Sixteen openings appear in the schedule. Six are new work and ten are existing to remain — on a renovation that split is the scope.
| # | Quantity & the basis it rests on | Value | Grade |
|---|---|---|---|
| 26 | New openings: five SW-1 wood doors at 3'-0"×7'-0" in gypsum walls, plus one SF-1 interior storefront at 3'-0"×7'-0"Door schedule, sheet A1200, hard count | 6 openings | GOLD |
| 27 | Existing to remain: three 6'-0" pairs at exterior walls, one 5'-0" pair, six 3'-0" singlesDoor schedule, marks prefixed EX- | 10 openings | GOLD |
| 28 | Openings visible on the floor plan — 16 single swing, 5 double swing, 1 slidingMachine detection on the plan. The excess over the schedule is openings in adjacent un-renovated space, correctly omitted from the schedule. Reported so the two counts can be reconciled rather than silently averaged. | 20 detected | SILVER |
| 29 | Hollow metal frames — SDI A250.8, min 0.053" uncoated steel, full-profile welded, prime finish, three anchors per jamb, mineral-fibre packedSection 081213 | 16 ga welded | GOLD |
| 30 | Flush wood doors — five-ply solid core, opaque paint finish, factory primed and machined, WDMA Heavy Duty Custom gradeSection 081416 | solid core | GOLD |
| 31 | Interior storefront — aluminium framed, non-thermal, clear anodic finish, stick system, 1-3/4" wide-stile doorSection 084113 | 1 system | GOLD |
| 32 | P-2 finish on door frames — specified for new AND existing frames, plus existing handrailsSection 099123 §3.5.B. Easy to miss: the existing frames are in the painting scope. | new + existing | GOLD |
| 33 | Door hardwareSection 081416 §3.1.A directs the reader to 'Section 087100 Door Hardware'. That section does not exist in the manual. Hardware is defined only by a schedule on the drawings. RFI. | no section | FLAGGED |
Wall Finishes (measured, not bid by Mindatu)
Recorded because the wall systems drive the drywall finish level and the wet-area board question. Mindatu measures every trade — and never bids any of them. Your back office, never your competitor.
| # | Quantity & the basis it rests on | Value | Grade |
|---|---|---|---|
| 34 | P-1 — water-based catalyzed epoxy over latex primer, SW 7641 Colonnade GrayFinish schedule; Section 099123 §2.4.C, §3.5.C.3 | 13 rooms | GOLD |
| 35 | P-3 accent — same epoxy system, SW 6213 Halcyon Green (Manicure/Pedicure, Reception, Clinic, Shampoo)Finish schedule | 4 rooms | GOLD |
| 36 | EP-1 — pre-catalyzed epoxy semi-gloss, restrooms and janitorFinish schedule; Section 099123 §2.4.B | 3 rooms | GOLD |
| 37 | FRP — Marlite pebbled panel, all sides of mop sink, floor to 5'-0" AFF and 5'-0" horizontallyKeynote TA-22 on the plan; product in Section 102800 §2.2.H — not in Division 6 or 9 where a reader would look for it | 1 location | GOLD |
What the documents could not support · 10 items
Ten gaps, named before bid day.
Every one of these is a real gap in a real issued bid set. They are published because an estimator pricing this scope needs them before bid day, not after.
- Division 07 does not exist in this project manual. There is no thermal-insulation section and no penetration-firestopping section, though six other sections cross-reference '078413 Penetration Firestopping' as if it were issued.
- The only firestopping specification in the manual is embedded inside Section 220529, a plumbing hangers-and-supports section. Wall and ceiling firestopping has no home.
- No tiling section exists anywhere in the manual.
- Level 5 gypsum finish is not specified, though epoxy wall coatings are.
- No moisture- or mold-resistant gypsum board is specified for the two restrooms or the janitor room.
- Section 087100 Door Hardware is cross-referenced by the wood-door section but was never issued.
- The finish-schedule tag BL-E appears on eight rooms and is decoded nowhere in the manual.
- Floor preparation over the existing slab is not addressed, in a renovation with a urethane sealer over the full floor area.
- The reflected ceiling plan's legend calls AC-2 'moisture resistant'; the specified product is described as high-washability. Same panel, different language.
- The drawn ceiling grid does not extend over every scheduled ceiling area, which is what defeated the second measurement (see worked example).
Provenance
Where this schedule comes from.
- Source
- NC eVP solicitation 132-WPCC-2026 — bid opened 14 July 2026, closed. Documents are public record. Mindatu did not bid this project and holds no interest in it.
- Set
- Construction Documents, 50 sheets, dated 06/08/2026, with 723-page Project Manual
- Measured
- 29 July 2026 — machine-assisted, estimator-verified line by line
- Rights
- No drawing sheet or specification page is reproduced here. What is published is Mindatu's own quantity schedule, method and limitations.
Step 2 of the deliverable chain
The takeoff is step one. Step two prices it in your workbook at your rates, with the provenance page on top — see a real one, client redacted, numbers real.
Send one invitation.
Forward the bid invite you are working on right now — portal link and all — to cs@mindatu.com. The complete graded takeoff comes back free, inside 2 business days.
Free → 3 × $99 → $200 / takeoff → $300 estimate + proposal → department from $500/wk